Updated September 2026
Dholera current status.
The honest version, in three columns: what is finished and running, what is being built right now, and what exists only as an approval. Most pages about Dholera blur these together. This one does not.
Finished
Built and running today.
You can go and stand next to all of this. It exists.
72km of roads
Internal road network in the Activation Area, 18 to 70 metres wide, with utilities underneath.
Complete
22.54sq km
The Activation Area, where trunk infrastructure has been developed.
Complete
109km expressway
Ahmedabad to Dholera, four lanes and access controlled, open to traffic since March 2026.
Open
50MLD water
Water treatment plant commissioned about 5 km away, scalable to 150 MLD.
Running
500MVA power
Distribution capacity across two Torrent Power substations, scalable to 1,500 MVA.
Running
300MW solar
Commissioned and generating, out of a solar park planned at up to 5,000 MW.
Running
In progress
Under construction now.
Work is visibly happening on all of these. None of them is finished.
Dholera International Airport
On 1,426 hectares about 20 km from Dholera, built by DIACL. Phase one approved June 2022 at ₹5,083 crore. Reported at around 80 percent complete.
BuildingTata and PSMC semiconductor fab
India's first commercial chip fab, an investment of up to ₹91,000 crore. Civil work passed the halfway mark in 2026 and cleanroom fit out has started.
BuildingBhimnath Dholera freight rail
A last mile freight line under implementation by Western Railway, linking to the Dedicated Freight Corridor near Ahmedabad.
BuildingSocial infrastructure
A multi speciality hospital, an integrated school, a fire station, investor accommodation and a food court, all listed as upcoming inside the Activation Area.
BuildingPrivate development
More than 1,000 studio apartments with commercial space by GAP Associates, and a 100 room corporate hotel by the Seksaria Group, both on the High Access Corridor.
BuildingApproved only
Real decisions, no construction.
These have government approval and budgets. That is not the same as a site with people on it, and the difference matters when someone is pricing a plot on the strength of them.
Ahmedabad Dholera metro
A 100 km elevated line in two phases, approved centrally in 2021 at an estimated ₹12,500 to ₹13,000 crore and targeted for 2027.
ApprovedSemi high speed rail
A passenger line planned from Ahmedabad along the expressway alignment for commuter movement.
PlannedDholera sea port
Sanctioned by the Gujarat Maritime Board in June 2020, with full operation expected between 2027 and 2028.
PlannedTP schemes 5 and 6
Planning work on expansion beyond the Activation Area began in 2025. The land is zoned. Nothing is serviced.
PlannedRoughly 400 sq km of the 422 sq km developable region is outside the Activation Area. Most of it has no infrastructure in the ground yet. If a plot is being sold to you on the strength of the metro or the port, you are buying an approval, not a service.
How it got here
The official timeline.
Eighteen years from a corridor decision to an expressway carrying traffic. The pace tells you more than any projection.
- 2008
Dholera approved as a node under the Delhi Mumbai Industrial Corridor.
- 2009
Gujarat enacts the Special Investment Region Act and notifies Dholera SIR.
- 2010
DSIRDA established as the regional development authority.
- 2011
Master planning work begins, led by Halcrow.
- 2012
The ICT master plan is prepared, and the development plan and control regulations are sanctioned.
- 2013
Programme managers appointed. All six town planning schemes sanctioned, covering 422 sq km.
- 2014
Environmental clearance received.
- 2016
DICDL formed as the SPV. Implementation starts on TP 2A and 4A, the 22.54 sq km Activation Area.
- 2019
The ABCD building and the City Integrated Operations Centre become operational.
- 2022
Trunk infrastructure operational across the Activation Area. Airport phase one approved.
- 2023
Construction begins on Dholera International Airport.
- 2026
The Ahmedabad to Dholera expressway opens to traffic.
Timeline follows the official Dholera SIR record. Updated September 2026.